A running snapshot of where the build is. Update this file as things move.

Status at a glance

SubsystemStatusNotes
System spec (RO-SPEC-001)Rev G — publishedRegulatory traceability added (NSF/ANSI 61, MFF)
Tank sourcing (T-101, T-102)Spec publishedLooking at modified Sanke kegs as primary path
Metering pumpsSpec publishedThree identical diaphragm pumps
Bill of materialsRev F — currentSee BOM
PLC / controlsParts being acquired (Phase 1)Productivity2000 P2-550 ordered
VFDsPhase 2 — eBay watchHighest path-dependency item
Sensors / instrumentsPhase 3Not started
Output devicesPhase 4Not started
HMIPhase 5Not started
Physical assemblyPhase 6Not started
Permitting (San Diego DEH)Pre-submittalSee regulatory

Recent changes

  • BOM moved to Rev F
  • System spec advanced to Rev G with regulatory traceability
  • Site published at water.paleotreats.com

Next milestones

  1. Finalize tank sourcing — confirm Sanke keg modifier or commit to custom build
  2. PLC bench setup with first I/O test
  3. Initial draft of HMI screens
  4. Pre-submittal meeting with San Diego DEH